Jharkhandother
Rashmi Construction
Promoter registered with Jharkhand RERA
3
registered projects
0
completed
2
in progress
0
lapsed / revoked
0
with extended deadlines
91
units in total
Active in Ranchi (2), Nagri (1); first registration 15 Sept 2022.
Projects
Project
Promoter
Status
Completion
Harmony Yakshit Heights
Nagri · JHARERA/PROJECT/59/2026
Rashmi Construction
Mixed use · 26 units
Registeredreg. 18 Aug 2025
completion by1 Nov 2028
Harmony Residency
Ranchi · JHARERA/PROJECT/6/2024
Rashmi Construction
Residential · 48 units
Registeredreg. 23 Oct 2023
completion by23 Feb 2027
Harmony Homes
Ranchi · JHARERA/PROJECT/42/2023
Rashmi Construction
Residential · 17 units
Validity endedreg. 15 Sept 2022
completion by15 Sept 2025
A promoter's record here is only what the Jharkhand registry publishes under this exact name or id. The same company can appear under several names, and group companies register separately.