31
registered projects
19
completed
12
in progress
0
lapsed / revoked
0
with extended deadlines
1,701
units in total
Active in Ernakulam (16), Kozhikode (5), Thrissur (3), Kottayam (3), Thiruvananthapuram (2), Pathanamthitta (1), Kannur (1).
Projects
Project
Promoter
Status
Completion
Skyline Grand Terrace
Kozhikode · K-RERA/PRJ/176/2020
M/s Skyline Builders
Residential · 19 units
Completed
completion by30 Jan 2022
Skyline Blue Vista
Kozhikode · K-RERA/PRJ/175/2020
M/s Skyline Builders
Residential · 96 units
Completed
completion by30 May 2023
Skyline Avenue Suites
Thrissur · K-RERA/PRJ/168/2020
M/s Skyline Builders
Residential · 75 units
Completed
completion by30 Jul 2023
Skyline Windmill
Pathanamthitta · K-RERA/PRJ/170/2020
M/s Skyline Builders
Residential · 84 units
Completed
completion by30 Jul 2024
Skyline Polaris
Ernakulam · K-RERA/PRJ/169/2020
M/s Skyline Builders
Residential · 47 units
Completed
completion by31 Jan 2024
Skyline Epic
Ernakulam · K-RERA/PRJ/172/2020
M/s Skyline Builders
Residential · 29 units
Completed
completion by30 Oct 2022
Skyline Opus
Ernakulam · K-RERA/PRJ/171/2020
M/s Skyline Builders
Residential · 53 units
Completed
completion by30 Jul 2022
Skyline Hazel
Kottayam · K-RERA/PRJ/034/2021
M/s Skyline Builders
Residential · 60 units
Completed
completion by31 Mar 2026
Skyline Xylus
Ernakulam · K-RERA/PRJ/097/2021
M/s Skyline Builders
Residential · 51 units
Completed
completion by31 Jul 2025
Skyline Aristocrat
Ernakulam · K-RERA/PRJ/173/2020
M/s Skyline Builders
Residential · 18 units
Completed
completion by28 Dec 2021
Skyline Pearl
Kottayam · K-RERA/PRJ/300/2020
M/s Skyline Builders
Mixed use · 65 units
Completed
completion by30 Sept 2024
Skyline Pixel
Ernakulam · K-RERA/PRJ/182/2020
M/s Skyline Builders
Residential · 77 units
Completed
completion by1 Aug 2024
Skyline Ranch Villas-Phase 2
Ernakulam · K-RERA/PRJ/013/2021
M/s Skyline Builders
Residential · 31 units
Completed
completion by30 Jun 2023
Skyline the One
Ernakulam · K-RERA/PRJ/ERN/075/2021
M/s Skyline Builders
Residential · 26 units
Completed
completion by19 Nov 2026
Skyline Ozone
Ernakulam · K-RERA/PRJ/ERN/125/2022
M/s Skyline Builders
Residential · 50 units
Completed
completion by31 Aug 2027
Skyline Zen
Ernakulam · K-RERA/PRJ/ERN/150/2022
M/s Skyline Builders
Residential · 44 units
Completed
completion by14 Oct 2027
Skyline Wings
Kannur · K-RERA/PRJ/KNR/155/2022
M/s Skyline Builders
Mixed use · 68 units
Registered
completion by29 Feb 2028
Skyline City Light
Thrissur · K-RERA/PRJ/TSR/021/2023
M/s Skyline Builders
Residential · 40 units
Registered
completion by28 Jun 2028
Skyline Matrix
Ernakulam · K-RERA/PRJ/ERN/059/2023
M/s Skyline Builders
Residential · 38 units
Completed
completion by30 May 2028
Skyline Central Avenue
Kottayam · K-RERA/PRJ/KTM/095/2023
M/s Skyline Builders
Other · 47 units
Completed
completion by30 Jun 2024
Skyline Odyssey
Kozhikode · K-RERA/PRJ/KKD/228/2023
M/s Skyline Builders
Residential · 86 units
Registered
completion by30 Apr 2029
Skyline Zest
Ernakulam · K-RERA/PRJ/ERN/230/2023
M/s Skyline Builders
Residential · 36 units
Registered
completion by30 Apr 2029
Skyline Vistara
Thrissur · K-RERA/PRJ/TSR/001/2024
M/s Skyline Builders
Residential · 54 units
Registered
completion by30 Apr 2029
Skyline Sanctuary
Ernakulam · K-RERA/PRJ/ERN/067/2024
M/s Skyline Builders
Other · 106 units
Completed
completion by30 Oct 2025
Skyline Hilltop
Ernakulam · K-RERA/PRJ/ERN/183/2024
M/s Skyline Builders
Residential · 102 units
Registered
completion by1 Feb 2030
Skyline Urban Oasis
Thiruvananthapuram · K-RERA/PRJ/TVM/229/2024
M/s Skyline Builders
Residential · 48 units
Registered
completion by1 Apr 2030
Skyline Beleza
Kozhikode · K-RERA/PRJ/KKD/004/2025
M/s Skyline Builders
Residential · 62 units
Registered
completion by1 Jul 2030
Skyline Dynasty
Ernakulam · K-RERA/PRJ/ERN/054/2025
M/s Skyline Builders
Mixed use · 73 units
Registered
completion by30 Apr 2030
Skyline Urban Oasis 2
Thiruvananthapuram · K-RERA/PRJ/TVM/102/2025
M/s Skyline Builders
Residential · 46 units
Registered
completion by1 Oct 2030
Skyline Marina Bay
Kozhikode · K-RERA/PRJ/KKD/016/2026
M/s Skyline Builders
Mixed use · 24 units
Registered
completion by14 Apr 2031
Skyline Zora
Ernakulam · K-RERA/PRJ/ERN/061/2026
M/s Skyline Builders
Residential · 46 units
Registered
completion by28 Feb 2029